What is Clause 2 for an employer's requirements under the RIAI Blue Form of Contract in Ireland for a residential project:
- Rory Connolly
- 17 hours ago
- 2 min read

Clause 2: The Employer’s Requirements
Project ScopeThe Employer is desirous of carrying out a small refurbishment and extension at [Project Address]. The Works shall include, but are not limited to:
Internal refurbishment of existing structures, including mechanical and electrical upgrades.
Construction of a [Specify Size] sqm extension to the existing building.
Structural alterations where required to integrate the new extension with the existing building.
Upgrades to finishes, fixtures, and fittings as per the contract documents.
Any necessary external works, including drainage, paving, and landscaping.
Contract and Obligations
The Works shall be executed under the terms of the RIAI Blue Form of Contract (With or Without Quantities) as applicable.
The Contractor shall ensure compliance with all Planning Permissions, Building Regulations, and Health & Safety requirements under Irish law.
The Works shall be completed within the agreed contract period of [Specify Duration] weeks from the commencement date.
Quality and Standards
All materials and workmanship shall conform to Irish Building Regulations, current industry standards, and manufacturer specifications.
The Contractor shall engage competent subcontractors and specialists where required, subject to the Architect’s approval.
The Employer reserves the right to inspect and approve all works at key milestones before proceeding to subsequent stages.
Contractor’s Responsibilities
The Contractor shall provide a programme of works detailing key activities, milestones, and completion dates.
The Contractor shall be responsible for site management, security, waste disposal, and maintaining a safe working environment.
Any deviations from the contract documents must be submitted for approval before execution.
Payment & Retention
Payment shall be made in accordance with the agreed stage payments set out in the contract.
A retention percentage of [Specify %] shall be held for [Specify Retention Period] post-completion, subject to the resolution of defects.
Defects and Completion
The Contractor shall be responsible for rectifying defects within the Defects Liability Period as per the contract.
Practical completion shall only be certified when all works comply with the contract requirements and statutory approvals.
Insurance and Indemnity
The Contractor shall provide evidence of valid Public Liability Insurance, Employers’ Liability Insurance, and Contractors’ All Risks Insurance before commencing works.
The Contractor shall indemnify the Employer against any claims arising from negligence, non-compliance, or defective work.