top of page

Understanding Liquidated Damages


In construction projects, liquidated damages (also known as delay damages) are a sum of money that is agreed upon in advance by the parties to the contract as compensation for any delays in completing the project. They are typically included in the contract as a way to incentivize the contractor to complete the work on time, as well as to compensate the owner for any losses they may incur as a result of the delay.

The amount of liquidated damages is typically based on the expected impact of the delay on the owner's business, such as lost profits or additional financing costs. It is important to note that liquidated damages are not meant to punish the contractor, but rather to provide a fair and reasonable estimate of the damages that the owner will incur as a result of the delay.

In order for liquidated damages to be enforceable, they must be a reasonable estimate of the actual damages that the owner is likely to incur as a result of the delay. If the amount of liquidated damages is found to be unreasonable or excessive, a court may reduce or even eliminate the damages owed.

It is also important to note that liquidated damages are not the same as damages for defective work or other breach of contract. In those cases, the damages will be based on the actual harm suffered by the owner as a result of the defective work or breach of contract, rather than a pre-agreed upon amount.


There are several methods that can be used to calculate liquidated damages in construction contracts, including the following:

  1. Percentage of contract value: This method involves calculating liquidated damages as a percentage of the contract value. For example, if the contract value is €100,000 and the liquidated damages rate is 1%, the total liquidated damages would be €1,000.

  2. Daily or weekly rate: This method involves calculating liquidated damages based on a set rate per day or week of delay. For example, if the daily rate is €1,000 and the project is delayed by 10 days, the total liquidated damages would be €10,000.

  3. Lost profit method: This method involves calculating the expected profit that the owner would have made if the project had been completed on time, and using that amount as the basis for the liquidated damages.

  4. Cost plus method: This method involves calculating the actual costs incurred by the owner as a result of the delay, such as additional financing costs or lost revenue, and using that amount as the basis for the liquidated damages.

It is important to note that the method chosen for calculating liquidated damages should be carefully considered and clearly stated in the contract, as it will have a significant impact on the amount of damages that may be recovered in the event of a delay.

Featured Posts
Recent Posts
Archive
Search By Tags
Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
bottom of page