How long will a Disability Access Certificate take to process?The timescale is up to 8 weeks under Section 6(5) of the Building Control Act, 1990, or longer if agreed between the applicant and the Building Control Authority.
The timescale is up to 8 weeks under Section 6(5) of the Building Control Act, 1990, or longer if agreed between the applicant and the Building Control Authority.